Phase 4: System Load and Configuration
Tas k Date Completed
Participate in the Phase 4 conference call
Verify receipt of ShoreGear equipment
Reserve IP addresses for your network
Configure server with the appropriate server operating system
Load the ShoreGear software
Enter the database configuration for ShoreGear
Confirm your ShoreTel System installation and cut-over dates
Confirm installation and cut-over coverage
Verify racking is complete
Verify power is in compliance
Verify UPS is installed
Verify cabling is complete
Verify ventilation upgrade is complete
Verify new phones and headsets have been delivered
Verify your System Administrators have been trained
Schedule training for your Operators and Workgroup(s)