Phase 4: System Load and Configuration Getting Started 1
ShoreTel 14 Planning and Installation Guide 23
Phase 4: System Load and Configuration
Phase 5: Installation Readiness Review
Table 4: System Load and Configuration
Task Date
Completed
Participate in the Phase 4 conference call
Verify receipt of ShoreTel equipment
Reserve IP addresses for your network
Configure server with the appropriate server operating system
Load the ShoreTel software
Enter the database configuration for ShoreTel
Confirm your ShoreTel System installation and cut-over dates
Confirm installation and cut-over coverage
Verify racking is complete
Verify power is in compliance
Verify UPS is installed
Verify cabling is complete
Verify ventilation upgrade is complete
Verify new phones and headsets have been delivered
Verify your System Administrators have been trained
Schedule training for your Operators and Workgroup(s)
Table 5: Installation Readiness Review
Task Date
Completed
Participate in the Phase 5 conference call
Upgrade desktops, if necessary, and ensure readiness for Client
software installation
Notify users of the ShoreTel system implementation
Verify telephone trunk lines are installed and tested
Verify server appliance is installed
Configure on-hour and off-hour schedules for Auto-Attendant menus
and Workgroups
Configure your Workgroups